Home > Business > Steel Plants > Iron Making

Iron Making

Overview

The sinter facility is used for the process of making sintered ore measuring 5 - 50 mm by mixing natural iron ore powder with cokes and calcium oxide.

Based on our proven technology capability and the experience we have gained over a long period of time, we provided the design, procurement, construction and commissioning of sinter facilities at home and abroad, including sinter plants at integrated steelworks in Indonesia and Brazil.

Further, we successfully completed the sinter plant projects in the Pohang and Gwangyang steelworks, the BSL sinter plant revamping project in Australia, the ESCO sinter plant project in Iran. Especially, No.5 sinter plant at Gwangyang steelworks is the world's largest sintering plant with capacity of 600㎥.

Key Projects

PROJECT LIST

  • Indonesia PT.KP No.1 Sinter Plant

    Indonesia PT.KP No.1 Sinter Plant

    Indonesia PT.KP No.1 Sinter Plant is to provide Sinter Ore into newly installed Integrated Steel Mill at Cilegon, Indonesia.

    ◆ Project period: May. 2011 ~ Dec. 2013
    ◆ Effective suction area: 450m²
    ◆ Production: 12,870 T/D
    ◆ Productivity: 28.6 T/D/m²
    ◆ Availability: 95%

    레이어 닫기
  • Korea POSCO Gwangyang No.5 Sinter Plant

    Korea POSCO Gwangyang No.5 Sinter Plant

    POSCO Gwangyang No.5 Sinter Plant at Gwangyang steelworks in Korea is the world's largest sinter plant.

    ◆ Project period: Aug. 2009 ~ Feb. 2011
    ◆ Effective suction area: 600m²
    ◆ Production: 24,180 T/D
    ◆ Productivity: 40.3 T/D/m²
    ◆ Availability: 98%

    레이어 닫기
  • Australia BSL sinter plant

    Australia BSL sinter plant

    BSL project was performed to replace worn out equipment in accordance with increasing productivity(+1,100,000T/Y, 20%UP) and long term operation in BSL No. 3 Sinter plant Australia (5,500,000 T/Y).

    ◆ Project period: Feb. 2007 ~ Apr. 2009
    ◆ Effective suction area: 420m² → 480m²
    ◆ Production: 15,000 T/D c 18,000 T/D
    ◆ Productivity: 40.5 T/D/m²
    ◆ Availability: 93%

    레이어 닫기
  • Korea POSCO Gwangyang No.2 sinter plant revamping

    Korea POSCO Gwangyang No.2 sinter plant revamping

    This RMHF(Raw Material Handling Facility) is to provide coke, iron ore and sub-materials into newly installed FINEX(1.5 millions T/Y) in Pohang Steelworks. It includes material yard, stacker/reclaimer, belt conveyor, crushing and screening equipments and etc.

    ◆ Project period: Dec. 1996 ~ Dec. 2007
    ◆ Effective suction area: 420m²→ 480m²
    ◆ Production: 15,000 T/D c 18,000 T/D
    ◆ Productivity: 40.5 T/D/m²
    ◆ Availability: 93%
    ◆ Bed Height: 850 mm → 1,000 mm
    ◆ Shut down period: 36 Days

    레이어 닫기