PTT LNG Terminal (Phase II)

PTT LNG Terminal (Phase II) was POSCO E&C’s first LNG EPC project in Thailand. The contract was awarded by PTT LNG, the ordering authority, and the project was executed in consortium with IHI Japan. 

The project site is located in the Map Ta Phut Industrial Estate of Rayong, Thailand and consisted of constructing two LNG tanks and the auxiliary facilities. Through the development of a long term relationship with the PTT Group, POSCO E&C was awarded an additional contract for the extension of a gasification and transmission facility following the successful completion of this project, where we delivered the detailed engineering, procurement, installation, preliminary pilot operation, and commissioning operation. 

POSCO E&C continues to strive in gaining furtherer presence in Thailand’s LNG market.

  • Period
    Period
    2014.02 - 2017.06
  • Place of order
    Place of order
    PTT LNG Co., Ltd.
  • Construction details
    Construction details
    Petrochemical facility extension
    - Cumene production by 327,000 tons/year
    - Phenol production by 250,000 tons/year
    - Acetone production by 154,000 tons/year

    Site area: Approx. 60,000 m2

    Work details: Detailed design, procurement, construction, preliminary pilot operation, commissioning operation

    Key equipment:
    - 2 LNG tanks
    - #2 jetty extension
    - Gasification/transmission and auxiliary facilities
  • Location
    Location
    Map Ta Phut, Rayong, Thailand