ANSAN S-POWER Combined Cycle Power Plant

The goal of this project was to build a large-scale combined cycle power plant in Ansan-si. For this project, Samchully, Korea South-East Power Co., and POSCO E&C jointly established a special purpose company (S-Power). 

H-class gas turbine is a state-of-the-art high-efficiency gas turbine befitting the ESG era. By cooperating with major gas turbine makers, we secured competitive power suitable for the project implementation. 

Large-scale combined power generation will replace the conventional coal-fired power generation in the era of coal phase-out. Accordingly, by accumulating large-scale combined power plant performances, we prepared a foundation to solidify our position as a global top player in the major overseas markets in Southeast Asia, South America, and the Middle East.

  • Period
    Period
    2012.11 - 2014.12
  • Place of order
    Place of order
    S-POWER
  • Construction details
    Construction details
    Power generation capacity: 834 MW × 1
  • Location
    Location
    An-San Si, Korea