POSCO Gwangyang Works Phase 5 Coke Making Plant project was to build the fifth cokes plant of Gwangyang Steelworks in line with the increased demand for high-quality cokes supply at Gwangyang Steelworks. The new cokes plant consists of the cokes ovens facilities, formulation facilities, CDQ facilities, sorting facilities, and transportation equipment.
POSCO E&C participated in the project by forming a consortium with overseas partners (Uhde, NSE and Shalke) and played a leading role in design, supply of equipment and materials, and installation. Based on the experience of completing various steelmaking facility installations and with skilled technological human resources, we successfully completed the project within the specified period. Since then, we have been playing the role as a leading company of the consortium for the PT.KP Cokes project in Indonesia, CSP Cokes project in Brazil, and POSCO Pohang Steelworks' Phase 6 Coke Making Plant project.